AnsweredAssumed Answered

"The operation failed to complete within the specified timeout period."

Question asked by anonymous on Dec 30, 2013
Latest reply on Dec 30, 2013 by anonymous
Hello, everyone.

I have a problem about handling Agilent DMM Connectivity Utility. Please help :(

The situation is...

I'm using 34401A Multimeter and it's well connected to PC through 34398A RS-232 Cable using USB to Serial Converter.

Baud Rate : 300
Stop Bit : 1
Data Size : 8
Parity : None
Flow Control : None
SRQ line : RI (default, I dun know exactly.)


Software works as you can see in the attached file named 'untitled.png'.

And also does fine at first when I click 'start to acquisition'.

But soon (after few secs) it stopped and says,

"The operation failed to complete within the specified timeout period." (you can see 'untiled1.png')

I don't know why. Any idea? Plz?  

Attachments

Outcomes